Proposed Construction Timeline

Project Milestones

2024

March

  • March 11
    Construction fence is Installed
     
  • March 13
    Groundbreaking Ceremony
    View Invitation PDF
     
  • March 22
    Asbestos Abatement begins
     
  • March 25
    Construction work begins with:
    • Demolition of current locker rooms and west end stairwell 
    • Renovations within Pennoyer School
    • Construction of building addition

2023

December

  • December 5
    Construction Bond Sale Closes
     
  • December 13
    Board Meeting: BOE Awards the Bid to Troop Construction Inc. for $7,888,000

November

  • November 2
    Bid Becomes Public
     
  • November 8
    Mandatory Pre Bid Meeting
     
  • November 14
    Construction Bond Sale
     
  • November 29
    Bid Opening

September

  • September 19
    DLA Architects meet with Pennoyer faculty to finalize design ideas
     
  • September 19 @ 6:30 pm
    DLA Architects meet with Pennoyer Facilities Committee
    View Facilities Committee Meeting
    View Presentation PDF
     
  • September (Various Dates)
    Construction Preparation Site Surveys

August

  • August 9
    DLA Architects Present Project and Phases to the Board of Education
    View Presentation at Board Meeting
     
  • August 17
    DLA Architects meet with Pennoyer faculty to discuss design ideas

July

  • July (Various Dates)
    Internal Project Discussions

June

  • June 20
    DLA Architects meet with Pennoyer administration to review drafts

May

  • May 10
    DLA Architects meet with Pennoyer administration to present potential timelines 

April

  • April 4
    Passed Referendum
     
  • April 12
    DLA Architects meet with Pennoyer administration to beginning project planning